Pharmacy site progress

/Pharmacy site progress

March 2014

Passive House Pharmacy latest site news

By | March 10th, 2014|Pharmacy site progress|

Time lapse video of work so far.. Passive House Pharmacy continues on site   Site Inspection 23rd August 2014 We are dealing with snag items in the pharmacy and the apartment is about 4 days from completion. [...]

Comments Off on Passive House Pharmacy latest site news

February 2014

PassivHaus Pharmacy progress

By | February 11th, 2014|Pharmacy site progress|

Passive House Pharmacy continues on site  Site Inspection 21st February 2014 It's a very cold February to be standing around on site looking at details for two hours, but site inspections have to be one [...]

Comments Off on PassivHaus Pharmacy progress

January 2014

Passive House Pharmacy Construction Update – Cavity wall details

By | January 13th, 2014|Pharmacy site progress|

Passive House cavity wall construction The passive house pharmacy and apartment building is beginning to take shape! Since I last reported the precast concrete floor slabs have arrived and external cavity wall construction has started. [...]

Comments Off on Passive House Pharmacy Construction Update – Cavity wall details

October 2013

News! Passive House Pharmacy continues on site!

By | October 21st, 2013|news, Pharmacy site progress|

Week Five Its hard to believe we are 5 weeks into a 51 week program. Foundation and demolition are ongoing. We have had to change to a sleeveless pile given the gravelly ground conditions and [...]

Comments Off on News! Passive House Pharmacy continues on site!